The building, blasting and coating of 554 blocks for the 2 vessels has been completed. Keel laying in dry dock no. 1 and no. 2. was done by end of February 2021. At this stage the erection of the blocks continues.
FATs of ship’s equipment, factory acceptance tests, have been attended at the various makers located between Schenzhen and Dalian. Equipment is ready to be installed according to the building process.