At the time being we are building 7 MRs and 2 LR1s oil/chem tankers simultaneously. For the supervision we have a team of 20 supervisors at GSI Long Xue.
The first MR tanker has been on sea trial and here after named Torm Strength. The vessel met all specification and contract requirements and is now under completion and soon ready for delivery. The next 2 MR vessel are at the outfitting pier. 3 more MRs are in dry dock no. 1 and the seventh is at block stage. The 2 LR1 vessel are being assembled in dry dock no. 2.